Technical Visit and Post Study Tours will be organized after the symposium respectively. Participants taking part in the technical visit will visit Yellow River Museum, the dike of Yellow River, laboratories and the exhibition of Digital Yellow River. Those who will take part in post-study tours will not only visit dam projects, but also enjoy the beautiful local scenes.
 
| Route | Duration | Participation | Cost / per person | 
| Techinical Visit | 30 Sept. (1 day)  | Participant | $300  | 
| Accompanying person | $200  | 
| Tour A  | 1-3 Oct.(3 days) | Participant | $750  | 
| Accompanying person | $600  | 
| Tour B  | 1-3Oct.(3 days) | Participant | $800  | 
| Accompanying person | $700  | 
  
  Technical Visit —1 day  (Sept. 30, 2011 )
  
  
  Yellow River Museum
  
  
  
  Yellow River dike
  
  
  Laboratories and the exhibition of Digital Yellow River
  
  
  Post Study Tour A—3 days, 2 dams ( Oct. 1-3, 2011 )
 
| Date | Activity | Lodge | 
| Oct. 1 | ·             Driving To Visit Shaolin Temple In Dengfeng | Yingbin Hotel of The Yellow River Henan in Zhengzhou | 
| Oct. 2 | ·            Drivng to visit Xiaolangdi Project, Driving to visit Yellow River-Crossing Project of South-to-North Water Diversion Middle Route Project ·               | Yingbin Hotel of The Yellow River Henan in Zhengzhou | 
| Oct. 3 | ·                      Visit Longmen Grottoes                         Visit Baima Temple | Yingbin Hotel of The Yellow River Henan in Zhengzhou | 
| Oct.4 | ·             Finish the Tour after Breakfast |    Zhengzhou | 
  
 
  Shaolin Temple
  
   
 
  Baima(White Horse)Temple
  
  Xiaolangdi Project
  Earth Core Rockfill Dam
  H=160m
  Installed Capacity:1800MW
  
  
Yellow River-Crossing Project
  
  Post Study Tour B —3 days .3 dams ( Oct. 1-3, 2011 )
 
 
 
|  Date | Activity | Lodge | 
| Oct. 1 | ·             Driving to Yichang City by Bus(about 8 hours)  | Three Gorges Project Hotel in Yichang  | 
| Oct. 2 | AM | ·             Visit Three Gorges Project  | Shuibuya Project Hotel | 
| PM | ·             Driving to Shuibuya project in Qingjiang | 
| Oct. 3 | ·             Vistit Shuibuya Hydropower Project  ·             Visit Geheyan Hydropower Project | Qingjiang Hotel in Yichang | 
| Oct.4 | ·             Finish the Tour after Breakfast | Yichang | 
   
 
  
  Three Gorges Project
  Concrete Gravity Dam
  H=181m
  Installed Capacity: 22400MW
  
  
  Shuibuya Hydropower Project
  CFRD
  H=233m
  Installed Capacity: 1840MW
  
  
  Geheyan Hydropower Project
  Concrete Gravity-arch dam
  H=151m
  Installed Capacity: 1200MW