
China Three Gorges Corporation (CTG) announced that it has
installed the rotor for the NO.2 power unit in the Karot hydropower project in
Pakistan on August 8, a milestone that lays a solid foundation for the
subsequent final assembly and scheduled commissioning.
The hoisting operation, which saw the rotor slowly hoisted
from the assembling chamber and then precisely placed into the turbine pit,
took 45 minutes.
The Karot hydropower project has installed 4 hydraulic
generators with a rated power of 180 MW, whose rotors have a diameter of
13.04 meters and a height of 1.84 meters, and the hoisting weight of a single
rotor and lifting appliance reaches 680 tons.
Source:China Three Gorges Corporation