BRIEFING OF THE LIUXIHE HYDROPOWER STATION IN GUANGDONG PROVINCE
I. General Description
The Liuxihe Hydropower Station is located in the vicinity of Conghua City, 90 km away from Guangzhou City in Guangdong Province. The dam site is seated on the gorge 1.3 km downstream of Xiaochuan village in Huangzhulang township. It is mainly for power generation and concurrently for flood control, irrigation, etc., which is a multi-purpose, comprehensive utilization median-sized hydro-project.The Liuxihe river basin is situated on north eastern to Guangzhou City, standing between Beijiang River and Dongjiang River, the topography of which is long-shaped in southern north and shallow-shaped in eastern west. Above the dam site, there is mountainous hilly region with precipitous topography. The Liuxihe is of the water system in delta estuary area, a tributary of the Pearl River Basin, having a total length of 157 km and a catchment area of 2296 km2. In the river basin, 37 km above the dam site, the controlled catchment area is 539 km2, sharing 23.5 % of the total.
The said river basin is situated on the Tropic of Cancer, featuring subtropical zone climate. The average annual design runoff is 1856 mm, the measured average annual runoff being 2078.5 mm. The design average annual oncoming discharge into the reservoir is 21.4 m3/s, whereas the measured value of which is 21.8 m3 /s after being put into commissioning. The design average annual volume of oncoming water is 675 million m3, whereas the measured value of which is 688 million m3. The total reservoir capacity is 375.8 million m3, the corresponding reservoir capacity at normal pool level being 325 million m3, while the dead reservoir capacity being 325 million m3, the benefit creation reservoir capacity being 239 million m3. The coefficient of reservoir capacity is 0.354, which is of an incomplete reservoir for over-year storage.
The Liuxihe hydropower Station is a composite hydropower station, being composed of a concrete arch dam, a subsidiary earth dam, a water diversion and surge tank system, an underground power house and a flood discharge system, etc., being altogether 5 parts.
The project was begun constructing on August 1956. The reservoir impounding was commenced on 20th June 1958. The No.1 power set was put into commissioning and linked to the power grid on 15th August 1958 and the No.2, 3, 4 power sets were put into operation on 17th September, 29th November and 23rd December of the same year in succession respectively.
The project was designed in accordance with 100-year flood, the design food level being 238.5 m (now adopting 237.60 m as approved by the former Ministry of Water Conservancy and Electric Power Industry), the check flood level was designed according to 1000-year flood ( now adopting 238.45 m as approved by the said ministry). The normal high water level is 235.0 m, whereas the drawdown water level of the design year is 226.0 m, the dead water level being 213.0 m and the limited water level for power generation being 211.0 m.
II. Characteristic Indexes of the Main Hydraulic Structures
1.Dam
The main dam of the Liuxihe Reservoir is a concrete, double-curvature, single arch dam. The elevation of the dam crest is 240.0 m, the width of the crest being 2.0 m, the maximum bottom width of the dam being 22 m, the arc length of the dam crest being 255.5 m, the maximum dam height being 78 m. The total volume of concrete placement of the arch dam is 130,000 m3. The foundation grouting is 4,560 m, the gallery grouting being 2600 m, the structural joint grouting being 9,060 m. The excavation of rock and earth work for arch dam foundation was begun from September 1956 to April 1957, totaling 65,880 m3. The concrete placement was started from April 1857 and completed on September 1958. The condition of engineering geology in dam site area is good with deep layer of granite, which is of densely crystalline sound and hard rock. It is of Jurassic and Cretaceous period in geology.
The earth dam of the project is a subsidiary dam, blocking up the low-lying land around the peripheral edge of the reservoir area. After the completion of Huanglongdai Reservoir on June 1975, the other side of the earth dam is Huanglongdai reservoir, which became to retain water at both sides. The dam is a homogenous earth dam with a dam crest elevation of 241.7 m, a dam length of 220 m, a dam crest width of 4 m and a dam bottom width of 210 m. In original design, the maximum dam height is 28.5 m. After being checked by PMF standard, the dam is required to be upgraded, the maximum height of which was revised to be 29.7 m. The earth-fill work of the earth dam is 350,000 m3.
2. Flood discharge structures
The flood discharge system has adopted a combined form of free surface spillway on arch crest and associated with flood discharge tunnel.There are 7 free surface spillways being provided at the arch dam crest, with a width of 11.5 m, a height of 4.0 m for each bay opening. The elevation of the crest weir is 235.0 m. The maximum discharge of each opening is 141 m3/s. The operation mode is of free surface spilling flow. A sky jump energy dissipater with differential high and lower sill is adopted. The flood discharge tunnel,built on the right-bank, embraces a total length of 237 m, which is a free surface flow tunnel. One set of steel plain gate is equipped to control the flow. The elevation of entrance bottom sill is 224.9 m, The cross section of the tunnel is of a horse-shoe type, 7.2 m wide, 8.9 m high, being capable to have a maximum design discharge of 1070 m3/s.
3. Water diversion structures
The power tunnel is provided at the right bank, embracing a total length of 1928.07 m, with a circular cross section. A part of the tunnel has concrete lining, with an inner diameter of 4.5 m, whereas the inner diameter of the unlined part is 6 m. The top elevation of the morning-glory haped entrance is 217.10 m, the bottom sill elevation being 206.5 m, the centerline elevation being 208.75 m. The mode of water diversion is of pressurized flow diversion, the maximum discharge available being 51.4 m3/s. At the end of the power tunnel, a differential surge shaft is provided, after which a penstock is provided, having a length of 140.0 m and an inner diameter of 4.5 m.
4. Power station
An underground powerhouse is adopted in the Liuxihe Hydropower Station. The power house is located on the right bank downstream of the dam, in which 4 T-G sets are installed. In original design, the installed capacity is 4 x 10.5 MW. Since 1993, the power sets are enlarged and upgraded. After completion, the installed capacity is turned to be 4 x 12.0 MW. The design average annual output is 154.6 million kWh, the firm output being 138 million kWh ( P=90 %). In actual performance, the average annual output is 146.7 million kWh. The original Model of the hydro-turbine is HL38---LJ---140, while the Model of the power generator is TS---286/135---12. At present, the Model of the hydro-turbine is HLA553---LJ---140, while the Model of power generator is TS---260/135---12.
III. Color Photos
![]() Photo 1.
Fragrant Creek Garden (Main entrance of the power plant) |
![]() Photo 2.
A long rainbow sleeping on the crystal clear pool (Bird eye view of the arch dam) |
![]() Photo 3.
An arch dam calming the stream (Upstream view of the
arch dam) |
![]() Photo 4 A
magnificent view of the arch dam (Looking up at the arch dam from downstream) |
![]() Photo 5 Underground power house |
IV. Distinguishing features and characteristics in technological aspects in the construction of Liuxihe Hydropower Station in Guangdong Province
The Liuxihe Hydropower Station has been one of the key engineering constructions listed in the state-run first Five-Year plan. It has also been one of the great practice of the State-run hydropower construction, following the building of Fuziling, Guanting, Gutianxi first phase, first stage of cascade development, Shizitan, Meishan and Shangyoujiang. It is the seventh median-sized hydropower station after the founding of New China, being a multi-purpose project mainly for the exploitation of water power resources. The river basin planning work was started on September 1955, while the preliminary design was begun conducting on January 1956. The said project was begun constructing on August 1956, the first power set was put into operation on August 1958 and all four power sets were put into commissioning in the same year.
1. The characteristic features of the project
The river bed at the dam site of the Liuxihe Hydropower Station appears in V-shape. All mountain slopes are steep and precipitous. The bed rock is of granite with simple geological structure. The dam has adopted a variable radius and variable central angle as well as variable thickness circular arc, concrete double-curvature arch dam. The characteristic ratio of bottom width and dam height is B/H = 0.283, being the first thin arch dam ever adopted in China during that time.
The overflow spillways are provided at the arch dam crest, which is the first case of flood spilling at the arch dam crest. There are seven bays of spillway, without the provision of gates at the dam crest, being of the free surface spilling type. The sky jump energy dissipater with apron sills at high and low levels are installed at the end of spillway, thus making the water flow mutually collided in open air for energy dissipation. In later stage, for the sake of convenience in flood dispatching, mitigating the erosion of dam foundation due to flood discharging from surface spillway, a flood discharge tunnel was built on the right bank in addition to other discharge facilities, thereby making possible to adopt a combined flood discharge scheme. The flood discharge tunnel is mainly responsible for flood release associated with the flood discharge function of the spillway on the arch dam crest.
In 1969, a flexible rubber dam was additionally built on the weir crest of the spillway, acting as a controlling gate to retain flood, which could be used for power generation during the tail period. Hence, it is possible to elevate the pool level 2 m, thus increasing power generation benefit.. Owing to the instability of air pressure within the collapsible rubber dam bag, causing surplus discharge and endangering the downstream flood control safety, the flexible rubber dam was dismantled in 1987.
The reservoir was built without reserving a bottom outlet for reservoir emptying.A water depth of 30 m still remained in front of the dam, the corresponding reservoir capacity of roughly 45 million m3 failed to be emptied. Once the safety problem of the arch dam encountered, it will be more difficult to strengthen the project or to take any remedy measures.
2. Characteristic features of the project construction
The main engineering quantity of the Liuxihe Hydropower project are: earth and rock excavation work 680,000 m3, earth-fill work 250,000 m3, concrete placement 187,000 m3. As the hydro-project is located in the narrow gorge, the general layout of the construction site is more difficult.
A semi-automatic concrete mixing plant is employed for dam concrete. Light rail concrete transfer truck and 9-ton gantry crane., etc. are adopted for mechanized construction. The effective period of construction for concrete placement reached nearly 12 months. The average monthly volume of placement reached 11,000 m3, the peak monthly placement being 20,600 m3. The coefficient of non-uniformity is 1.8 --1.9. The fourth grading concrete is used for dam proper, the max. grain size of aggregate being 150 mm. The #140 - #250 concrete are used for different parts of the dam project. The design criterion of concrete is 120 day-strength, combined materials additives, plasticizing agent, stone block buried are used in concrete mixing. Attention is fully paid on lowering the placing temperature and heat dissipation. problems. During early stage, design has been made to reserve heat dispersion shaft within the dam proper. Such a scheme, after being carefully studied and compared, it has been revised to adopt the method of adding cooling water and mixing acicular ice as well as burying cooling water pipes within the dam proper, thereby conducting new technique of I-phase and II-phase cooling. It has yielded promising and successful results.
During the high peak period of construction for the Liuxihe Hydropower Station, the total labor force reached 14,000 persons. There are nearly 5 million labor-day to complete the said hydropower station. All items of temporary structures are nearly 100,000 m3. During peak period, the monthly power consumption for construction reached 1.30 million kW.h.
3. Fast in construction speed
The general progress of construction for Liuxihe Hydropower Station is: the planning work of Liuxihe River Basin was started on September1955. The preliminary design was completed on June 1956, altogether lasting 9 months. The project was formally started constructing on August 1956 and the first power set was put into operation on August 1958, the construction of which lasted 2 years. The station was wholly completed on January 1959, the total construction period was less than 2 years. As a whole, the Liuxihe Hydropower Station, starting from the commencement of river basin planning up to fully completion, altogether lasted less than three and half years. The construction speed is comparatively fast.
4. Low in engineering cost
On the aspect of dam site selection, the Liuxihe Hydropower Station has screened five dam sites. In accordance with the concrete topography, geological condition, interfaced with the comparison of various dam types, finally the fourth dam site was selected, where dam site rocks are relatively sound, with thinner layer of weathering and lower in investment. In dam type selection, five alternative schemes have been compared, in which the arch dam is the most preferable for its least investment, being equivalent to 2/3 that of gravity dam or rock-fill dam. In the aspect of engineering quantity, the amount of excavation and residue cleaning as well as the concrete of the dam proper is relatively less in amount. In the design of arch dam, the dam crest spillway scheme has been adopted, which is simpler in layout and economical in engineering cost as compared with river bank spillway and water release outlet within dam proper. Based on the geological condition, a length of 800 m of the power tunnel could merely use shotcrete in stead of concrete lining, thereby reducing the engineering quantity and saving investment. In the layout of power house, the main power house is arranged in line with the subsidiary power house and the central control room is situated on one terminal of the main power house, thus forming a compact arrangement and consequently reducing the engineering quantity. Owing to the fact that optimization has been carried out in the design and the optimal scheme has been selected and the new structure and new technology have been adopted, thus making the investment of cost estimate per unit kW reduced to 1100 yuan (rmb).
The cost saving measures were employed during construction, such as: in the aspect of technologies, as regard to the livelihood during construction, the bamboo structures were adopted for office building and the bamboo reinforced concrete structures were used for the partition wall of warehouse for materials. The upstream cofferdam designed is of rock-fill bodies overflow type. In order to save cement, the coarse aggregates with the max. grain size of 150 mm were adopted in dam concrete. Furthermore, 5 % - 10 % of white soil or 1 % platicizer, 7 % buried stone block were used as additives or coarse aggregate. To utilize later age strength after 120-day as design criteria and to use different grade concrete at different places, etc. are all effective measures to save cement. In the aspect of management, to implement budget of construction drawings, engineering task list, limited amount material list, etc. to reinforce cost management in an overall point of view, to pay serious attention to cost analysis, to combat waste and to establish award for reasonable suggestions, award for saving in engineering issues.
As grave attention has been paid on the saving measures both in technology and management during construction, the actual engineering cost is 40.54 million yuan, being reduced 13.7 % of the total cost estimated., the cost per unit kW being 965 yuan (rmb). The cost was relatively low for a median-sized hydropower station during that time. After 40 years operation, it has witnessed that the saving measures taken in construction did not influence the engineering quality, which was esteemed to be good and promising.
5.Excellent in quality
The attention has been strongly focused on the engineering quality by the construction unit of the Liuxihe Hydropower Station. Various measures have been taken, to observe strictly the quality control procedure. In order to well construct the arch dam, a strict and reasonable organizational design of construction has been made. More strict requirement has been proposed for the excavation treatment for the dam foundation, the in-situ inspection and acceptance as well as the quality control of concrete. With an aim at controlling the precise dimensions of the dam block of a double-curvature arch dam in concrete placement, specific persons have been appointed by the engineering bureau to compute every layer and every block in advance. In order to guarantee the quality of construction, the experiment personnel have been specifically trained. Experiment laboratory has been established. With an aim at controlling the temperature of concrete, the pre-cooling of concrete and cooling water pipes have been buried within the dam. Simultaneously, systems of quality monitoring and accident treatment, etc. have been established together with strict implementation.
All measures implemented during construction have ensured the quality of construction for the project. No crack has been found in the dam proper. The quality of grouting for transverse joints is excellent. The deformation of arch dam is quite small after reservoir impounding. No leakage in the concrete dam proper has been found. The vibration of dam proper during flood discharging is slight. The power tunnel after being put into operation, despite a part of the tunnel has not been lined with concrete, however, the surrounding rocks remain stable.
The Liuxihe Hydropower Station has been put into operation for more than 40 years. However, up to the present moment, all items of the main structures have had smooth functioning, enjoying good praise from various aspects.
6.Briefing on the operation situation of the arch dam
Owing to the fact that the Liuxihe Hydropower Station is reasonable in design and strict in construction, therefore, the quality of the project is excellent. During the past 40 odd years, the project is in smooth operation and normal management. The first periodic inspection on dam safety was carried out in 1989. The appraisal made by the specialist panel witnessed the fact the Liuxihe arch dam has been esteemed as C-class (normal) dam. In 1997, the project has been registered by the dam safety supervisory center as an A-class dam. The second periodic inspection on dam safety has been started from 1999 and will be completed in the first half year of 2000.
The present items and apparatus for safety monitoring in Liuxihe Hydropower Station are: 1. horizontal displacement, new and old video level line system, arch crown inverted plumbing line, dam shoulder inverted plumbing line, geodetic quadrangle plan control net; 2. vertical displacement; 3. variation of structural joints;crack observation on downstream dam surface.
The displacement on Liuxihe arch dam has regular variation on one side, and the non-reversible displacement toward upstream is in existence, which tends to be essentially stable at present. After being operated for 40 odd years, the concrete of arch dam proper has had nice outer appearance. Generally speaking, the overall situation is relatively good. The weathering and erosion phenomena on both upstream and downstream concrete dam surfaces are not serious. Only an extremely small part has naked its coarse aggregates, while most part of the concrete surface are smooth and flush. However, cracks were found on the dam surface during the early stage and operation period, among which the cracks occurred on the downstream surface were more numerous. Practically, no leakage was found either on dam proper or on dam foundation. Besides, the property of cracks is pending further investigation to be clarified. The remaining situations could witness that the structural behavior of the dam is excellent and promising.
7. Precious experience
The completion of Liuxihe Hydropower Station is an important starting point.It is not only served as a creative work for the development of electric power industry in Guangdong Province, it has also accumulated precious experience of hydropower construction. Furthermore, it has trained a lot of personnel and technical mainstay as well. Since 40 odd years?operation and commissioning of the station, it has provided low-price power for industrial and agricultural production of the Guangdong Province. It has played evident role for flood control, irrigation and domestic use for the local people. The Liuxihe Hydropower Station is the first hydropower station in Guangdong Province since the founding of New China. It has shouldered the responsibility of training task, training the operation personnel at various levels for other provinces and districts and providing a good base for practice, as well as playing an important role for the development of hydropower undertakings.
กก
กก