Briefing of Jiangya Dam
In order to accelerate the
harnessing of Lishui River, to tap its water resources and to develop economy in the
basin, Ministry of Water Resources, People's Republic of China (MWR) and Hunan Provincial
Government (HPG) jointly established Lishui Hydro and Power Corporation (LHPC) in 1992,
which is responsible for the construction, operation and management of water and power
projects and related economical projects in Lishui River basin within Hunan Province. Located in the middle reaches of Yangtze River, the Lishui River, with a total catchment area of 18,583km2, a total length of 390km and a drop of 1439m, extends across Hunan and Hubei Provinces. A total of 26 cascade projects are to be built on its main stream and tributaries. Jiangya Project is the first one built by LHPC. Jiangya Dam is located in the middle reaches of Loushui River, a tributary of Lishui River, 57km away from Cili County, Zhangjiajie Prefecture, as the first critical flood control project on the Lishui basin. The catchment area above Jiangya damsite is 3711km2, the reservoir, being of one-storage, has a total storage capacity of 18.55〜106m3, out of which, 740〜106m3 for flood routing with a |
dead capacity of 410〜106m3 and a normal water level of 236.0m. After completion, the downstream flood protection level will be of 17-20 year frequency instead of 4-7 year frequency currently, which can greatly ease the flood control pressure in the Lishui Basin and western Dongting Lake; the reservoir irrigates 85,000mu of farmland, improves 124km of river course, and provides more than 5000 persons with water supply. In addition, adjacent to the world-famous Wulingyuan scenic spot, Jiangya Dam will become a new tourist spot. |
![]() |
Jiangya Dam, with a crest at E1. 245.0m, max. height of 131m and crest length of 369.8m is the highest full-section RCC gravity dam in the world of its kind at this time. The total dam concrete volume is 1.37〜106m3, of which 1.10〜106m3 for RCC. The spillway blocks are aarranged in the middle of the river bed with 4 crest spillways and 3 mid-level outlets. The high-low bucket is used for energy dissipation by means of big differential deflecting collision when the crest spillways and mid-level |
outlets discharge flood jointly. The Mid-level outlets discharge flood of 1700m3/s corresponding to 100-year frequency flood or below; mid-level outlets and crest spillways jointly discharge a max flood of 11700 m3/s above 100-year frequency flood. |
The powerhouse is built inside the mountain body on the right bank, the diversion system with a tower-shaped intake adopts one penstock to one unit layout with 3 parallel power tunnels in total, one tunnel has an internal diameter of 6m and a length of 158.04m. The main powerhouse has excavation dimensions of 108.5m〜20m〜46m (L〜W〜H), with a total installed capacity 3〜100MW, a design head of 80m, a flow rate of 141.39 m3/s for a turbine. The units can produce energy output of 756GW·h per year. Jiangya Dam project, as the national key project, commenced with its main |
|
body works in July, 1995 and was completed essentially by the end of 1999, has a total investment of 3313.72〜106 RMB yuan, of which 1.0〜109 RMB yuan from MWR and HPG, respectively, in addition to banks' loan (of which 97〜106 USD from the World Bank). |
|
During Jiangya RCC Dam construction, on the basis of full application of the up-to-date RCC construction technology, the dam contractor creatively developed a new RCC construction technology--Inclined-layer concreting method which made the concrete have an equivalent construction quality with some indexes more excellent in comparison with the traditional horizontal-layer concreting method, increased the construction efficiency and decreased the cost. A total of 455〜103m3 volume RCC was placed with the new technology, which had laid a foundation for the completion 8 months ahead of the schedule. In order to solve the difficulties of concrete haulage in the middle of the dam and above caused by the canyon |
topography at the damsite, a joint transportation system consisting of deep-chute & high-speed belt conveyan facilities and vacuum chutes was set up to convey concrete in great scale, resulting in economic and efficient transportation. The application of enriched & vibrated RCC (EVR) was popularized to the dam abutment and surrounding waterstops breaking through the design' limit, which not only ensured the construction quality and simplified the construction craft but also speeded up the construction. Officials from the World Bank and the experts from both at home and abroad highly appraised Jiangya RCC Dam construction quality. The construction technology applied to Jiangya Dam has pushed forward. the RCC construction technology in China. |
![]() |
|
|
|
Jiangya Project Data |
No | description | Unit | Quantity |
1 | Hydrology | ||
Catchment Area above Damsite | km2 | 3,711 | |
Annual Inflow | 106m3 | 4,160 | |
Design Flood Discharge (P=0.2%) | m3/s | 12,200 | |
Check Flood Discharge (P=0.02%) | m3/s | 15,700 | |
2 | Reservoir | ||
Design Flood Water Level | m | 239.1 | |
Check Flood Watear Level | m | 242.7 | |
Normal Flood Watear Level | m | 236.0 | |
Limit Water Level During Flood Season | m | 210.6 | |
Total Storage Capacity | 106m3 | 1,855 | |
Flood Control Capacity | 106m3 | 740 | |
Dead Storage | 106m3 | 410 | |
3 | Dam | ||
Type | RCC Gravity Dam | ||
Max. Dam Height | m | 131 | |
Crest length | m | 369.8 | |
4 | Flood Discharge Stucture | ||
Crest Spillway Gate (4 gates ) Dimensions | m〜m | 14〜15 | |
Mid-level Outlet (3 gates) Dimensions | m〜m | 5〜7 | |
Method of Energy Dissipation | Dissipation by Collision in the Air | ||
Design Flood Discharge | m3 | 9,251 | |
Check Flood Discharge | m3 | 11,700 | |
5 | Waterway System | ||
Type | Diversion Tunnel (3Tunnels) | ||
Tunnel Internal Diameter | m | 6 | |
Length of Each Tunnel | m | 158.04 | |
6 | Powerhouse | ||
Type | Underground Powerhouse | ||
Dimensions | m〜m〜m | 108.5〜20〜46 | |
Total Installed Capacity | MW | 3〜100 | |
Design Head | m | 80 | |
Firm Capacity | MW | 37.1 | |
Annual Generation | 106kW·h | 756 | |
7 | Navigation (shiplift on left bank) | ||
Capacity | t | 20 | |
Length | m | 935 | |
8 | Irrigation (irrigation intake on left bank) | ||
Irrigated Area | mu | 85,000 | |
Water Supply Capacity | person | 50,000 | |
9 | Main Civil Construction Volume | ||
Earth-rock Excavation | m3 | 1,138,000 | |
VCC | m3 | 454,000 | |
RCC (dam) | m3 | 1,100,000 | |
Reinforcing Steel | t | 3,830 | |
10 | Resettlement | person | 16,159 |
11 | Total Costs | 106RMB Yuan | 3,313.72 |
12 | Total Construction Duration | yr | 4.5 |